How High Volume Automotive Plants Cut Stamping Press Setup Time by 41.7% with SMED

How High Volume Automotive Plants Cut Stamping Press Setup Time by 41.7% with SMED

Every minute a bottleneck stamping press spends changing dies is a minute it can’t produce parts. For Autokiniton, a high-volume Tier 1 automotive supplier, shorter changeovers offered a way to recover production time on the presses that limited output.

GKW Business Solutions helped teams at 10 Autokiniton stamping facilities apply Single-Minute Exchange of Die (SMED), a Lean method for reducing changeover time. The first event at each facility cut setup time by an average of 41.7%, or 24.4 minutes per changeover.

Start with the press that limits output

GKW structured the work as a five-day SMED and Kaizen workshop. At each facility, a cross-functional team reviewed video of an actual setup on the bottleneck press. Watching the setup step by step helped the team spot waiting, unnecessary motion, and work it could move outside the shutdown window.

The teams used three questions to redesign the changeover.

  1. What can we prepare while the press is running? Look for work that can safely happen in advance, such as staging tools or preparing paperwork.
  2. What can we move out of the shutdown window? Change how a step is performed so it can happen before shutdown or after restart.
  3. How can we simplify the work that still requires a stopped press? Improve the sequence, put tools where they’re needed, and clarify who performs each step.

On day three, the teams tested their revised procedures and recorded what worked and where the sequence still needed improvement. The workshop also prepared Autokiniton team members to lead future SMED and Kaizen events.

What the first events delivered

All 10 facilities shortened setup time in their first events. One facility cut 49.7 minutes from its setup, a 57.7% reduction. Across the 10 facilities, setup-time reductions ranged from 17.1% to 76.9%.

Measure Result
Average setup-time reduction measured in the first events 41.7%
Average time saved per changeover in the first events 24.4 minutes
Projected annual press time recovered across 10 facilities Approximately 28,600 hours
Projected annual savings across 10 facilities, worst case $3.6 million
Projected annual savings across 10 facilities, likely case $5.4 million

The annual projections assume the other stamping presses at each facility would match the setup-time improvement measured on that facility’s initial press. To assess the value of a rollout, operations and finance can use actual changeover frequency and determine where the recovered time could support more shipments, reduce overtime, or free capacity for other work.

Make the faster changeover repeatable

The teams built press-by-press rollout plans with specific actions, expected time reductions, owners, deadlines, and funding needs. The plans included 5S, standard work, and operator training so other crews could follow the improved setup sequence.

Changeover frequency also helps determine where to go next. A press that changes dies several times a day can recover more production hours over a year than one with a larger time saving per setup and fewer changeovers. That gives plant leaders a practical way to prioritize the next event.

Are changeovers limiting output at your plant? Talk with GKW Business Solutions about a SMED pilot for your bottleneck process. We’ll help your team measure the current setup, test a better sequence, and estimate what a broader rollout could deliver.

Source — GKW Business Solutions SMED Case Study, June 17, 2024.